Construction Schedule (As on: 31-Oct-2018)

Corridor NumberCorridor Details
Corridor I Miyapur to LB Nagar
Stage 2 Miyapur to S R Nagar
Stage 5 S R Nagar to L B Nagar
Corridor II JBS to Falaknuma
Stage 6/1 JBS to MGBS
Corridor III Nagole to Shilparamam
Stage 1 Nagole to Mettuguda
Stage 3 Mettuguda to Begumpet
Stage 4 Begumpet to Shilparamam

 

Projects Updates

STAGEWISE DETAILS

StageTotal KmsScopeNo. of Stations
Stage-1 8.01 315 7
Stage-2 11.90 456 10
Stage-3 8.25 305 6
Stage-4# 11.47 441 10
Stage-5 17.31 652 17
Stage-6* 9.68 375 9
Total 66.62 2544 59

FOUNDATIONS COMPLETE

StageTotal CompletedViaductStations%Kms
Stage-1 315 245 70 100.0% 8.01
Stage-2 456 356 100 100.0% 11.90
Stage-3 305 245 60 100.0% 8.25
Stage-4# 410 308 102 93.0% 10.51
Stage-5 652 482 170 100.0% 17.31
Stage-6* 356 268 88 94.9% 9.15
Total 2494 1904 590 98.0% 65.13

PIERS COMPLETE

StageTotal CompletedViaductStations%Kms
Stage-1 315 245 70 100.0% 8.01
Stage-2 456 356 100 100.0% 11.90
Stage-3 305 245 60 100.0% 8.25
Stage-4# 408 306 102 92.5% 10.45
Stage-5 652 482 170 100.0% 17.31
Stage-6* 355 267 88 94.7% 9.12
Total 2491 1901 590 97.92% 65.04

SPAN ERECTION

StageTotal CompletedViaductStations%Kms
Stage-1 314 251 63 100.0% 8.01
Stage-2 455 365 90 100.0% 11.90
Stage-3 305 251 54 100.0% 8.25
Stage-4# 399 308 91 90.5% 10.27
Stage-5 651 498 153 99.8% 17.31
Stage-6* 340 259 81 90.9% 8.67
Total 2464 1932 532 96.89% 64.41

SEGMENTS CAST

Casting YardCasting Yard NameScope No.Segment Cast Nos.Cast %
1 Uppal 16500 15320 92.85%
2 Qutubullahpur 8423 8423 100.00%
  Total 24923 23743 95.27%

 

* Stage 6 Considered upto MGBS; # Stage 4 Considered upto Raidurg