Construction Schedule (As on: 31-Dec-2018)

Corridor NumberCorridor Details
Corridor I Miyapur to LB Nagar
Stage 2 Miyapur to S R Nagar
Stage 5 S R Nagar to L B Nagar
Corridor II JBS to Falaknuma
Stage 6/1 JBS to MGBS
Corridor III Nagole to Shilparamam
Stage 1 Nagole to Mettuguda
Stage 3 Mettuguda to Begumpet
Stage 4 Begumpet to Shilparamam

 

Projects Updates

STAGEWISE DETAILS

StageTotal KmsScopeNo. of Stations
Stage-1 8.01 315 7
Stage-2 11.90 456 10
Stage-3 8.25 305 6
Stage-4# 11.47 441 10
Stage-5 17.31 652 17
Stage-6* 9.66 375 9
Total 66.59 2544 59

FOUNDATIONS COMPLETE

StageTotal CompletedViaductStations%Kms
Stage-1 315 245 70 100.0% 8.01
Stage-2 456 356 100 100.0% 11.90
Stage-3 305 245 60 100.0% 8.25
Stage-4# 422 318 104 95.7% 10.84
Stage-5 652 482 170 100.0% 17.31
Stage-6* 358 270 88 95.5% 9.19
Total 2508 1916 592 98.6% 65.49

PIERS COMPLETE

StageTotal CompletedViaductStations%Kms
Stage-1 315 245 70 100.0% 8.01
Stage-2 456 356 100 100.0% 11.90
Stage-3 305 245 60 100.0% 8.25
Stage-4# 417 313 104 94.6% 10.69
Stage-5 652 482 170 100.0% 17.31
Stage-6* 356 268 88 94.9% 9.13
Total 2501 1909 592 98.31% 65.29

SPAN ERECTION

StageTotal CompletedViaductStations%Kms
Stage-1 314 251 63 100.0% 8.01
Stage-2 455 365 90 100.0% 11.90
Stage-3 305 251 54 100.0% 8.25
Stage-4# 404 309 95 91.6% 10.36
Stage-5 651 498 153 99.8% 17.31
Stage-6* 348 267 81 93.1% 8.88
Total 2477 1941 536 97.41% 64.71

SEGMENTS CAST

Casting YardCasting Yard NameScope No.Segment Cast Nos.Cast %
1 Uppal 16500 15523 94.08%
2 Qutubullahpur 8423 8423 100.00%
  Total 24923 23946 96.08%

 

* Stage 6 Considered upto MGBS; # Stage 4 Considered upto Raidurg