Project Updates

Project Updates

Construction Schedule (As on: 15-Mar-2019)

Corridor NumberCorridor Details
Corridor I Miyapur to LB Nagar
Stage 2 Miyapur to S R Nagar
Stage 5 S R Nagar to L B Nagar
Corridor II JBS to Falaknuma
Stage 6/1 JBS to MGBS
Corridor III Nagole to Shilparamam
Stage 1 Nagole to Mettuguda
Stage 3 Mettuguda to Begumpet
Stage 4 Begumpet to Shilparamam

 

Projects Updates

STAGEWISE DETAILS

StageTotal KmsScopeNo. of Stations
Stage-1 8.05 315 7
Stage-2 11.78 456 10
Stage-3 8.03 305 6
Stage-4# 11.47 441 10
Stage-5 17.42 652 17
Stage-6* 9.66 374 9
Total 66.41 2543 59

FOUNDATIONS COMPLETE

StageTotal CompletedViaductStations%Kms
Stage-1 315 245 70 100.0% 8.05
Stage-2 456 356 100 100.0% 11.78
Stage-3 305 245 60 100.0% 8.03
Stage-4# 441 337 104 100.0% 11.40
Stage-5 652 482 170 100.0% 17.42
Stage-6* 370 282 88 98.9% 9.57
Total 2539 1947 592 99.8% 66.26

PIERS COMPLETE

StageTotal CompletedViaductStations%Kms
Stage-1 315 245 70 100.0% 8.05
Stage-2 456 356 100 100.0% 11.78
Stage-3 305 245 60 100.0% 8.03
Stage-4# 436 332 104 98.9% 11.25
Stage-5 652 482 170 100.0% 17.42
Stage-6* 360 272 88 96.3% 9.28
Total 2524 1932 592 99.25% 65.82

SPAN ERECTION

StageTotal CompletedViaductStations%Kms
Stage-1 314 251 63 100.0% 8.05
Stage-2 455 365 90 100.0% 11.78
Stage-3 305 251 54 100.0% 8.03
Stage-4# 418 324 94 94.8% 10.77
Stage-5 651 498 153 99.8% 17.42
Stage-6* 356 275 81 95.5% 9.14
Total 2499 1964 535 98.31% 65.20

SEGMENTS CAST

Casting YardCasting Yard NameScope No.Segment Cast Nos.Cast %
1 Uppal 16500 15808 95.81%
2 Qutubullahpur 8423 8423 100.00%
  Total 24923 24231 97.22%

 

* Lengths of all stages adjusted according to CMRS application report. (Stage 4/1&4/2 cumulative data mentioned for Previous Report & Current Status section.

* Stage 6 Considered up to MGBS; # Stage 4 Considered up to Raidurg

* Stage 6 : Due to alignment revision one span length is reduced to 374 scope.